published Friday, June 28th, 2013

Cleanup of massive TVA ash spill concludes

Kingston ash spill cleanup nears completion
Robert Deacy, TVA's senior vice president of generation and construction, talks about the $1 billion Kingston Ash Recovery Project to restore land damaged by a toxic ash spill on Dec. 22, 2008.

The massive coal ash cleanup near a Tennessee Valley Authority coal-fired power plant in East Tennessee is wrapping up.

The Knoxville News Sentinel reported that, with the removal of a final pile of gray ash on Friday, the $1.1 billion removal of spilled ash will conclude.

TVA must still monitor layers of ash on the bottom of the Emory and Clinch rivers for 30 years. It was agreed that allowing the streams to naturally bury the ash under layers of sediment was the best solution for the underwater sludge.

It was on a frigid early morning on Dec. 22, 2008 that a containment cell at the Kingston Fossil Plant failed and some 5.4 million cubic yards of coal ash spread in what a local resident called an 8-foot-tall tsunami.

about Associated Press...

The Associated Press

videos »         

photos »         

e-edition »

advertisement
advertisement

Find a Business

400 East 11th St., Chattanooga, TN 37403
General Information (423) 756-6900
Copyright, Permissions, Terms & Conditions, Privacy Policy, Ethics policy - Copyright ©2014, Chattanooga Publishing Company, Inc. All rights reserved.
This document may not be reprinted without the express written permission of Chattanooga Publishing Company, Inc.